August 2015 (1)
June 2015 (1)
May 2015 (1)
February 2015 (1)
January 2015 (1)
November 2014 (2)
October 2014 (2)
September 2014 (6)
August 2014 (1)
July 2014 (5)
June 2014 (1)
March 2014 (3)
February 2014 (2)
January 2014 (1)
November 2013 (3)
October 2013 (1)
August 2013 (3)
July 2013 (4)
May 2013 (4)
April 2013 (3)
March 2013 (2)
February 2013 (3)
January 2013 (4)
December 2012 (6)
November 2012 (9)
October 2012 (10)
September 2012 (9)
August 2012 (14)
July 2012 (17)
June 2012 (14)
May 2012 (13)
April 2012 (18)
March 2012 (14)
February 2012 (10)
January 2012 (12)
December 2011 (8)
November 2011 (11)
October 2011 (10)
September 2011 (13)
August 2011 (10)
July 2011 (6)
June 2011 (12)
May 2011 (8)
April 2011 (8)
March 2011 (9)
February 2011 (6)
January 2011 (9)
December 2010 (8)
November 2010 (17)
October 2010 (8)
September 2010 (12)
August 2010 (15)
July 2010 (10)
June 2010 (15)
May 2010 (9)
April 2010 (11)
March 2010 (13)
February 2010 (10)
January 2010 (14)
December 2009 (14)
November 2009 (10)
October 2009 (17)
September 2009 (20)
August 2009 (18)
July 2009 (22)
June 2009 (12)
Answering Questions
Avista Utilities
Clark Fork
Community Service
Customer Service
Energy Assistance
Energy Efficiency
Environment Facts
Hydro power
Infrastructure upgrades
Lake Coeur d'Alene
Natural Gas
Power Outages
Reliability Facts
Renewable Energy
Renewable Facts
Smart Grid
Spokane River

New Clarkston-area natural gas line about one-quarter complete   

Tags: Avista Utilities, Washington, Natural Gas, Infrastructure upgrades

New line will reinforce gas service to Clarkston area customers; Safety lighting along trail a welcome public benefit

Post by Dan Kolbet

Pipe install
Welding pipe
Natural gas pipeline installation includes welding
sections of steel pipe together. The new line will
help reinforcegas service to Avista customers in
the Clarkston area.
Since mid-July Avista contract crews have been working on a 2.8-mile natural gas line extension in the Lewiston-Clarkston Valley that will help reinforce gas service to Avista customers in the Clarkston area.

The new six-inch steel high pressure natural gas line is being installed on the Clarkston, Wash., side of the Snake River and will be fed through an existing line from Lewiston, Idaho. The project comes with several unique challenges, such as shoreline work, trenching along a popular nature trail, and accessing land managed by the Army Corp. of Engineers and Department of Transportation. Crews have also hit unexpected sections of buried rock, which slowed trenching work.

Recently Avista also had to monitor a portion of the project located underneath the Southway Bridge for cultural artifacts. An archaeologist was onsite during construction to observe the pipeline installation, but found no cultural artifacts.

Associate Gas Engineer David Smith, who is managing the project, said that 4,100 feet of pipe has been installed so far. That’s about 28 percent of the total expected length of the project.

Avista customers and area residents have expressed positive feelings about the project according the Regional Business Manager Mike Tatko who has spoken about the project at several community events.

An additional benefit of the project to customers and the public came in the form of safety lighting on the Greenbelt Trail, a popular recreation area, where the new line is being installed. In order to install the new pipeline, Avista needed to access land managed by the Army Corp of Engineers. As in-kind consideration in lieu of fees for conducting this project, Avista will install 46 lights along the trail from Chestnut Beach to Swallows Boat Ramp parking lot, at an approximate cost of $71,500. The new lights, to be installed later this year, will improve the safety of visitors who use the Greenbelt Trail.

"We are pleased to partner with the Corps to install safety lighting along the Greenbelt Trail as a part of our natural gas pipeline project," Tatko said. “Keeping funds for this project local in the form of new trail lighting is a very visible benefit to Avista customers and all area residents who use the trail."

Installation of the pipeline is expected to be complete in November.

After the line is complete, it will be pressure tested at 1.5 times its normal pressure before natural gas is allowed to flow. It’s a check to ensure the line has no leaks and is safe for use.
Posted by  System Account  on  9/13/2011
0  Comments  | 0  Links to this post | Bookmark this post with:          


Add a Comment

We encourage comments on this blog, but this is a family friendly conversation, so please check out our discussion guidelines so we’re all on the same page. By submitting a comment, you agree to these terms and our Privacy Policy.  

Customers must have a My Account and be logged in to comment.
Login to My Account | Create My Account


We're hopeful that this space will encourage thought provoking and informative community discussions about issues related to our products and services. Currently you must be an Avista customer to participate in the conversation, but stay tuned. In the coming weeks we'll also provide an opportunity for non-customers to participate in this forum.