Avista is replacing nearly 9 miles of natural gas pipeline in Davenport, Wash. The project is estimated to cost more than $3 million. The work will be conducted May to October. |
Bring in the diggers and heavy equipment because construction is underway in Davenport, Wash., as Avista replaces nearly 9 miles of natural gas pipeline that’s approaching the end of its service life. The project carries a price tag of more than $3 million. It’s part of Avista’s commitment to maintain and upgrade our natural gas pipeline system.
From May through October, Avista-authorized contractor Loy Clark will be installing new natural gas pipelines in streets and alleys throughout Davenport.
As we replace the natural gas pipeline one section at a time, Davenport natural gas customers will experience a short interruption of service while we’re working on the natural gas pipeline in a specific area. Customers will be notified two days in advance of working in their neighborhood so they can plan ahead. Once the work is complete and service is restored, qualified Avista personnel or contractors will safely relight appliances, such as water heaters.
Attendance was light when we held an open house at the Davenport Memorial Hall on Wednesday, May 2, to answer questions about the project. Hopefully that means that folks in Davenport are comfortable with the project.
This six-month, $3 million project is just one example of how Avista must continually invest in maintaining and upgrading the natural gas pipelines that allow us to serve our customers.