August 2015 (1)
June 2015 (1)
May 2015 (1)
February 2015 (1)
January 2015 (1)
November 2014 (2)
October 2014 (2)
September 2014 (6)
August 2014 (1)
July 2014 (5)
June 2014 (1)
March 2014 (3)
February 2014 (2)
January 2014 (1)
November 2013 (3)
October 2013 (1)
August 2013 (3)
July 2013 (4)
May 2013 (4)
April 2013 (3)
March 2013 (2)
February 2013 (3)
January 2013 (4)
December 2012 (6)
November 2012 (9)
October 2012 (10)
September 2012 (9)
August 2012 (14)
July 2012 (17)
June 2012 (14)
May 2012 (13)
April 2012 (18)
March 2012 (14)
February 2012 (10)
January 2012 (12)
December 2011 (8)
November 2011 (11)
October 2011 (10)
September 2011 (13)
August 2011 (10)
July 2011 (6)
June 2011 (12)
May 2011 (8)
April 2011 (8)
March 2011 (9)
February 2011 (6)
January 2011 (9)
December 2010 (8)
November 2010 (17)
October 2010 (8)
September 2010 (12)
August 2010 (15)
July 2010 (10)
June 2010 (15)
May 2010 (9)
April 2010 (11)
March 2010 (13)
February 2010 (10)
January 2010 (14)
December 2009 (14)
November 2009 (10)
October 2009 (17)
September 2009 (20)
August 2009 (18)
July 2009 (22)
June 2009 (12)
Answering Questions
Avista Utilities
Clark Fork
Community Service
Customer Service
Energy Assistance
Energy Efficiency
Environment Facts
Hydro power
Infrastructure upgrades
Lake Coeur d'Alene
Natural Gas
Power Outages
Reliability Facts
Renewable Energy
Renewable Facts
Smart Grid
Spokane River

Crews create their own path to restoration   

Tags: Avista Utilities, Electricity, Power Outages, Washington, Idaho

Broken power pole
This power pole was ripped from the ground during a powerful storm in the
Lewiston/Clarkston Valley in early May. One damaged area was so
remote that our crews had to build a road to access it.
View photos on Flickr of the windstorm damage as well as the crews’ efforts in restoration.
View photos on Flickr of the windstorm damage as well as the crews’ efforts
in restoration. 
Post by Sarah Hilbert

When the power goes out – we go all-out for you. In early May, a strong windstorm in the Lewiston/Clarkston area caused many outages, taking out power to 18,000 customers at its peak. Poles were snapped in half and downed power lines were strewn about in hard-to-access areas throughout the Clarkston Valley.

One concentrated outage had taken out 7,526 customers. Most of our customers were restored after we rerouted power over serviceable power lines; however, a few customers remained out for hours until the final repairs were made. This post should give you an idea of what goes on during a large power outage.

This day was challenging because it involved a large number of damaged transmission structures/lines, which serve thousands of customers, plus distribution lines – which serve neighborhoods. Many of the lines were in very remote locations, which are difficult to access quickly.

All hands on deck
We were able to restore power to most of our customers in short order thanks to an all-hands-on-deck approach. We assessed the damage quickly and assisted the local first responders, while beginning the restoration work out of our Pullman and Clarkston offices.

Initially, crews could not even reach the most damaged feeder (a large power line serving many customers) because it was so remote. But within a few hours, we worked with customers to get approvals to access their property and contractors to use equipment to build a construction road, greatly decreasing the repair time. 

In order to get the materials we needed to get the lights back on, we had to pull items from several warehouses throughout our service territory – and fast. Even gas department employees (who don’t typically work on the electric service side) got in the mix by pre-assembling steel poles and transporting materials.

Hearing from you
Our Contact Center call volume spikes when large outages occur. More than 18,400 calls came in on during this storm day. Fortunately, 62 percent of the calls were handled through our automated phone system, doing the work of 150 full-time employees. This both saved you on-hold time and money, through fewer employees. Our reps personally handled nearly 7,000 calls, well into the night.

When the lights go out, you know we’re committed to getting you back on line as quickly and safely as possible. Yet we don’t often detail what lengths our employees in the field go through to restore power. This outage wasn’t typical, given the number of damaged structures, but our response was – working as a team to provide the best service possible for our customers.

View photos of the windstorm damage as well as the crews’ efforts in restoration. 
Posted by  System Account  on  6/9/2010
0  Comments  | 0  Links to this post | Bookmark this post with:          


Add a Comment

We encourage comments on this blog, but this is a family friendly conversation, so please check out our discussion guidelines so we’re all on the same page. By submitting a comment, you agree to these terms and our Privacy Policy.  

Customers must have a My Account and be logged in to comment.
Login to My Account | Create My Account


We're hopeful that this space will encourage thought provoking and informative community discussions about issues related to our products and services. Currently you must be an Avista customer to participate in the conversation, but stay tuned. In the coming weeks we'll also provide an opportunity for non-customers to participate in this forum.